Sudi 2021-WG-31 plot's future environment is successfully closed!

Author: ComeFrom: Date:2024/4/16 14:00:10 Hits:12
At 10:08 am on April 6, 2024, the Sudi 2021-WG-31 plot corridor and the "Future Ring" project in Zone D were successfully closed, marking a milestone victory for the project.
The total length of the "Future Ring" bridge is 289m, weighing about 900 tons. The main steel box girder is 2.8m wide and 1.5m high. To facilitate component transportation and on-site construction, it is divided into 19 sections and assembled into 11 lifting units on site.
After the docking of each section of the bridge body is completed, the docking position is supported by a Bailey frame to ensure that the weld strength meets the requirements. At the same time, dynamic inspection of the bridge body is carried out during the docking process: firstly, the seismic support located above the round steel column has an impact on the elevation of the bridge body; secondly, the angle control before the bridge body forms a ring is strictly checked and accepted in accordance with the drawings, laying a solid foundation for the smooth closure of the "future ring".( Information source: Zhongyifeng Green Construction Company)



Next:Nothing